Work Progressing nicely
20/03/20 15:57
Lots of progress to report, The plumbers have installed the oil tank and boiler, the upstairs radiators are all in position and mots of them are connected up to the pipework. The ground floor underfloor heating jigsaw in well underway with some of the rooms already completed. We can't commission the underfloor heating until the flagstones and laminate are in place. Some of the upstairs lights and sockets have been temporarily wired up to work.
The next steps are flagstone floor laying, installing the downstairs shower and decorating upstairs rooms.